COSL Onshore Rig Intake Verification Report

Type of audit

Rig Intake

Auditee/Customer

COSL Drilling Europe (CDE)
Wellesly

Date

2024/01/14
930 days ago

Findings

38
Number of findings

Status

In process
Stig Seland

COSL Onshore Rig Intake Verification Report
Summary

As a part of the rig intake and preparations for the Toppand East Exploration well and Gnomoria Appraisal well, Wellesley petroleum (Wellesley) performed an onshore Verification of COSL Drilling Europe AS (CDE) on both HSE- and technical aspects. The verification was held at CDE’s premises at Vestre Svanholmen 4, in Sandnes, 13-14th of December. The review was held in a good atmosphere, the CDE participants were very open and willing to explain and share information. The verification team identified two (2) non-conformances, zero (0) observations, three (3) improvement suggestions and 33 actions. None of the findings are considered critical for operation. The verification team’s impression is that CDE is a rig company that has a well-functioning business management system. CDE is ISO 9001, 14001, ISO 45001 and 50014. A separate competence review meeting will be scheduled closer to spud.

Findings

Non-Conformity Open

Open, Deadline was:

NC-1. Lack of documentation regarding chemicals used on the rig. Measurement program is lacking information regarding water treatment chemicals, hydraulic fluids, and lubricants (Vaptreat, Jet-Lube Kopr-Kote, Jet-Lube Alco 73, Houghto-Safe NL1).

Ensure that all required documentation as required in Aktivitetsforskriften §70 is in place. Responsible: S. Giljebrekke

Non-Conformity Open

Open, Deadline was:

NC-2. A HAZID for pipe handling was performed in 2019. The Offshore Norge recommended guidelines for remote pipe handling operations, section 5. Handling procedures shall be established for all planned manual pipe handling operations marked ”M” in the matrix. These procedures must be based on risk analysis (HAZID). HAZID shall be repeated at least every 3 years and in relation to changes that will affect the pipe handling.

Schedule a HAZID for pipe handling as soon as possible and latest before operation begins for Wellesley. Responsible: K. S. Nilsen

Improvement Open

Open, Deadline was:

IMP-1. Some of the references to NORSOK was not updated in Synergi. This should be corrected.

Update references to NORSOK in Synergi. Responsible: S. Giljebrekke

Improvement Open

Open, Deadline was:

IMP-2. The RIT recommends preparing a L3 procedure for handling of drones that lands on the rig.

Preparing a L3 procedure for handling of drones that lands on the rig. Responsible: S. Giljebrekke

Improvement Open

Open, Deadline was:

IMP-3. Working environment requirements from 3rd party equipment should be included in CDE checklist.

Include working environment requirements from 3rd party equipment in the CDE checklist. Responsible: J. Helle

Actions Closed

Closed Deadline was:

Action 1. CDE to send CDE presentation including updated org. chart. Responsible: M. Arthun

ÅKP. Received

Actions Open

Open, Deadline was:

Action 2. Forward list of internal deviations. Responsible: S. Giljebrekke

Actions Closed

Closed Deadline was:

Action 3. CDE to send information regarding compensating measures. Responsible: M. Arthun

ÅKP. Received

Actions Closed

Closed Deadline was:

Action 4. CDE to send a copy of a daily HSE rapport. Responsible: S. Giljebrekke

ÅKP. Recieved

Actions Open

Open, Deadline was:

Action 5. CDE to forward the 2024 QHSE Program Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 6. CDE to forward Promoters 2024 QHSE Plan Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 7. Forward agenda for Bi-weekly HSE meeting and suggest time for meeting. Responsible: M. Arthun

ÅKP. Agenda received but not time.

Actions Open

Open, Deadline was:

Action 8. CDE to forward plan for Operational and Organisational barrier monitoring. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 9. Inform RIT how the results from the QRA have been communicated to the Rig Personnel. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 10. CDE to forward a copy of the letter to Havtil regarding the last audit. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 11. CDE to forward a Synergi report with open findings from audits. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 12. CDE to forward External Audit plan for 2024. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 13. CDE to forward COPR internal audit plan for 2024. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 14. Plan for a joint audit of Subsea7 in January/February 2024. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 15. CDE to send a copy of the competence requirements Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 16. Schedule a competence review meeting close to spud. Responsible: M. Arthun

Actions Open

Open, Deadline was:

Action 17. Risk Exposed Group matrix to be forwarded. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 18. WEACHs to be forwarded. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 19. CDE to forward procedure for temporary equipment. Responsible: M. Arthun

Actions Open

Open, Deadline was:

Action 20. A new safety representative should be elected from the service companies Responsible: M. Laget

Actions Open

Open, Deadline was:

Action 21. Forward list of safety delegates and status on courses. Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 22. How are recommendations from the EPA communicated to the rig personnel? Responsible: S. Giljebrekke

Actions Open

Open, Deadline was:

Action 23. WE to send risk assessment of 3rd party chemicals, and all SDS to CDE QHSE Engineer. Responsible: H. Folkvord

Actions Open

Open, Deadline was:

Action 24. Rename “COSLPromoter kjølemedium Log” or “DM#6003507 Kuldemedium log COSLPromoter” to match each other and avoid confusion. Responsible: J. Helle

Actions Open

Open, Deadline was:

Action 25. Remove R-404A from rig and log if not in use. Responsible: J. Helle

Actions Closed

Closed Deadline was:

Action 26. Please forward the Synergi report for Contained rig and sustainability inspection carried out in May 2022. Responsible: S. Giljebrekke

ÅKP: Report received.

Actions Open

Open, Deadline was:

Action 27. CDE to provide info on how to get NOV to improve performance with regards to NPT. Responsible: K. S. Nilsen

Actions Open

Open, Deadline was:

Action 28. Wellesley to set up a separate meeting with Enhanced drilling regarding RMR and to include CDE. Responsible: M. Laget

Actions Open

Open, Deadline was:

Action 29 . CDE to provide latest result related to ESD test. Responsible: J. Helle

Actions Closed

Closed Deadline was:

Action 30. CDE to provide specification for the crane hook. Responsible: M. Anthun

Actions Open

Open, Deadline was:

Action 31. CDE to provide Wellesley with new helicopter certificate once obtained. Responsible: M. Anthun

Actions Open

Open, Deadline was:

Action 32. CDE to provide pit overview. Responsible: K. S. Nilsen

Actions Open

Open, Deadline was:

Action 33. Wellesley to look into the best comms solution for both Toppand East and Gnomoria. Responsible: M. Laget

Additional Documentation

TOP-WLSLY-D-RA-0900-Onshore-Rig-intake-verification-report_rev.-01Signed.pdf

TOP-WLSLY-D-RA-0900-Onshore-Rig-intake-verification-report_rev.-01Signed.pdf

New Audit Report

You do not have permission to view this form.