| Operator | Rig | Discipline / Origin | Project Phase | Well | Section | Date | What Happened | |
|---|---|---|---|---|---|---|---|---|
INEOS
2317 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | 6306/3-1 S Fat Canyon |
Production section | 09/12/2021 |
Extremely slow progress ranging from 1-10m/hr.
Likely due to sweeling/stickyness of clay due to use . . . Steinar Aarnes / Morten Laget |
PDF Edit |
INEOS
3407 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | PL937 Fat Canyon |
Intermediate section | 04/11/2021 |
ROP in 12 1/4″ section dropped to almost nothing at +/- 1900 m. Drilling parameters were varied, and . . . / |
PDF Edit |
INEOS
2269 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | 6306/3-1 S Fat Canyon |
Intermediate section | 31/10/2021 |
ROP dropped from 50 m/hr to 1 m/hr Drilling Supervisor / Morten Laget |
PDF Edit |