| Operator | Rig | Discipline / Origin | Project Phase | Well | Section | Date | What Happened | |
|---|---|---|---|---|---|---|---|---|
DNO
5911 – DNO
|
Deepsea Yantai | Drilling | Operational | 25/7-11 S Norma |
Reservoir section | 05/09/2023 |
Time drill to initiate KO with 2 m/hr. Good performance kicking off from mainbore, no problems Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5909 – DNO
|
Deepsea Yantai | Drilling | Operational | 25/7-11 S Norma |
P&A | 05/09/2023 |
Due to high percentage of gas in the mud return the interface had to go over the shaker system and . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5906 – DNO
|
Deepsea Yantai | Operational | 25/7-11 S Norma |
Reservoir section | 03/09/2023 |
The primary MDT tool and BU failed. A additional MDT tool was mobilized from Deepsea Stavanger. Drilling Engineer / Morten Laget |
PDF Edit | |
DNO
5872 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Surface section | 07/08/2023 |
the ROP is very slow ( 1-2 m/hr) after drilling approximately 1500 meters using XZ816 PDC bit. . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5867 – DNO
|
Deepsea Yantai | Subsurface Own Experience |
Operational | 25/7-11 S Norma |
Surface section | 30/07/2023 |
New version of the Gravitas earlier used. The WSG not used to the new version. Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5864 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
BOP running | 30/07/2023 |
Used two ROVs to guide the BOP on top of WHH. No problems. Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5859 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
Drawwork in landing mode. No change in hookload while cementing and displacing. Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5855 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
After the 30″ conductor shoe was drilled the inclination of the conductor increased. Used the WHRT . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5854 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
When checking for cement outside the condcutor there was no cement to be found on 3/4 of the sides. . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5145 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Intermediate section | 16/04/2023 |
FIT was a success. Shaved off 1.75 hrs compared to the test at 20″ shoe. 2.5 hrs vs 0.75 hrs. . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5124 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 |
Run mud mat with buoyancy marker. Mud mat covered in soil after completing RMR operation Drilling Engineer / Morten Laget |
PDF Edit |
PGNiG
4923 – PGNiG
|
Deepsea Yantai | Logistics Own Experience |
Planning | 6608/1-1 S Copernicus |
Other | 03/10/2022 |
With this focus the mobilization plan became a live document and with a weekly focus, ensuring all . . . Johan Kjos-Hanssen / Morten Laget |
PDF Edit |
PGNiG
4913 – PGNiG
|
Deepsea Yantai | Drilling | Operational | 6608/1-1 S Copernicus |
P&A | 23/09/2022 |
When pulling the conductor there was no cement stuck to it due to use of protane wrapping on the . . . Drilling Engineer / Morten Laget |
PDF Edit |
PGNiG
4921 – PGNiG
|
Deepsea Yantai | Logistics Own Experience |
Operational | 6608/1-1 S Copernicus |
Other | 20/09/2022 |
Due to late busy vessel schedule of PSV and MI Swaco vessel MS Norbar, mud for 8-1/2″ Section was . . . Johan Kjos-Hanssen / Morten Laget |
PDF Edit |
PGNiG
4922 – PGNiG
|
Deepsea Yantai | Logistics Own Experience |
Operational | 6608/1-1 S | N/A | 12/09/2022 |
Captain of the vessel suggested to use the Brine tank for the Premix as Premix does not contain . . . Johan Kjos-Hanssen / Morten Laget |
PDF Edit |
PGNiG
4844 – PGNiG
|
Deepsea Yantai | Marine Own Experience |
Operational | 6608/1-1 S Copernicus |
Top hole | 09/09/2022 |
Everything went according to plan and logging was done remotely. Final position report was delivered . . . Stian Engvik / Morten Laget |
PDF Edit |
PGNiG
4843 – PGNiG
|
Deepsea Yantai | Marine Own Experience |
Operational | 6608/1-1 S Copernicus |
Rig move | 09/09/2022 |
Bridge and marine reps was not informed from DSV or DE when required spud equipment was taken . . . Stian Engvik / Morten Laget |
PDF Edit |
PGNiG
4842 – PGNiG
|
Deepsea Yantai | Marine Own Experience |
Operational | 6608/1-1 S Copernicus |
Rig move | 09/09/2022 |
Marine reps identified possibility to start transit 2hrs before de-ballasting was completed. This . . . Stian Engvik / Morten Laget |
PDF Edit |
PGNiG
4840 – PGNiG
|
Deepsea Yantai | Logistics Own Experience |
Operational | 6608/1-1 S Copernicus |
Top hole | 04/09/2022 |
With good planning and cooperation, everything shipped to SSJ prior to operation start in due time. . . . Johan Kjos-Hanssen / Morten Laget |
PDF Edit |
PGNiG
4830 – PGNiG
|
Deepsea Yantai | Marine Own Experience |
Operational | 6608/1-1 S Copernicus |
Rig move | 29/08/2022 |
All tubulars were backloaded from the rig and mud and bulk tanks emptied. The rig was deballasted to . . . Phil Hardy / Morten Laget |
PDF Edit |