Lessons Learned749

Operator Rig Discipline / Origin Project Phase Well Section Date What Happened
DNO 5911 – DNO Deepsea Yantai Drilling Operational 25/7-11 S
Norma
Reservoir section 05/09/2023 Time drill to initiate KO with 2 m/hr. Good performance kicking off from mainbore, no problems
Drilling Engineer / Morten Laget
PDF Edit
DNO 5909 – DNO Deepsea Yantai Drilling Operational 25/7-11 S
Norma
P&A 05/09/2023 Due to high percentage of gas in the mud return the interface had to go over the shaker system and . . .
Drilling Engineer / Morten Laget
PDF Edit
DNO 5906 – DNO Deepsea Yantai Operational 25/7-11 S
Norma
Reservoir section 03/09/2023 The primary MDT tool and BU failed. A additional MDT tool was mobilized from Deepsea Stavanger.
Drilling Engineer / Morten Laget
PDF Edit
DNO 5872 – DNO Deepsea Yantai Drilling
Own Experience
Operational 25/7-11 S
Norma
Surface section 07/08/2023 the ROP is very slow ( 1-2 m/hr) after drilling approximately 1500 meters using XZ816 PDC bit. . . .
Drilling Engineer / Morten Laget
PDF Edit
DNO 5867 – DNO Deepsea Yantai Subsurface
Own Experience
Operational 25/7-11 S
Norma
Surface section 30/07/2023 New version of the Gravitas earlier used. The WSG not used to the new version.
Drilling Engineer / Morten Laget
PDF Edit
DNO 5864 – DNO Deepsea Yantai Drilling
Own Experience
Operational 25/7-11 S
Norma
BOP running 30/07/2023 Used two ROVs to guide the BOP on top of WHH. No problems.
Drilling Engineer / Morten Laget
PDF Edit
DNO 5859 – DNO Deepsea Yantai Drilling
Own Experience
Operational 25/7-11 S
Norma
Top hole 30/07/2023 Drawwork in landing mode. No change in hookload while cementing and displacing.
Drilling Engineer / Morten Laget
PDF Edit
DNO 5855 – DNO Deepsea Yantai Drilling
Own Experience
Operational 25/7-11 S
Norma
Top hole 30/07/2023 After the 30″ conductor shoe was drilled the inclination of the conductor increased. Used the WHRT . . .
Drilling Engineer / Morten Laget
PDF Edit
DNO 5854 – DNO Deepsea Yantai Drilling
Own Experience
Operational 25/7-11 S
Norma
Top hole 30/07/2023 When checking for cement outside the condcutor there was no cement to be found on 3/4 of the sides. . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5145 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Intermediate section 16/04/2023 FIT was a success. Shaved off 1.75 hrs compared to the test at 20″ shoe. 2.5 hrs vs 0.75 hrs. . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5124 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 10/04/2023 Run mud mat with buoyancy marker. Mud mat covered in soil after completing RMR operation
Drilling Engineer / Morten Laget
PDF Edit
PGNiG 4923 – PGNiG Deepsea Yantai Logistics
Own Experience
Planning 6608/1-1 S
Copernicus
Other 03/10/2022 With this focus the mobilization plan became a live document and with a weekly focus, ensuring all . . .
Johan Kjos-Hanssen / Morten Laget
PDF Edit
PGNiG 4913 – PGNiG Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
P&A 23/09/2022 When pulling the conductor there was no cement stuck to it due to use of protane wrapping on the . . .
Drilling Engineer / Morten Laget
PDF Edit
PGNiG 4921 – PGNiG Deepsea Yantai Logistics
Own Experience
Operational 6608/1-1 S
Copernicus
Other 20/09/2022 Due to late busy vessel schedule of PSV and MI Swaco vessel MS Norbar, mud for 8-1/2″ Section was . . .
Johan Kjos-Hanssen / Morten Laget
PDF Edit
PGNiG 4922 – PGNiG Deepsea Yantai Logistics
Own Experience
Operational 6608/1-1 S N/A 12/09/2022 Captain of the vessel suggested to use the Brine tank for the Premix as Premix does not contain . . .
Johan Kjos-Hanssen / Morten Laget
PDF Edit
PGNiG 4844 – PGNiG Deepsea Yantai Marine
Own Experience
Operational 6608/1-1 S
Copernicus
Top hole 09/09/2022 Everything went according to plan and logging was done remotely. Final position report was delivered . . .
Stian Engvik / Morten Laget
PDF Edit
PGNiG 4843 – PGNiG Deepsea Yantai Marine
Own Experience
Operational 6608/1-1 S
Copernicus
Rig move 09/09/2022 Bridge and marine reps was not informed from DSV or DE when required spud equipment was taken . . .
Stian Engvik / Morten Laget
PDF Edit
PGNiG 4842 – PGNiG Deepsea Yantai Marine
Own Experience
Operational 6608/1-1 S
Copernicus
Rig move 09/09/2022 Marine reps identified possibility to start transit 2hrs before de-ballasting was completed. This . . .
Stian Engvik / Morten Laget
PDF Edit
PGNiG 4840 – PGNiG Deepsea Yantai Logistics
Own Experience
Operational 6608/1-1 S
Copernicus
Top hole 04/09/2022 With good planning and cooperation, everything shipped to SSJ prior to operation start in due time. . . .
Johan Kjos-Hanssen / Morten Laget
PDF Edit
PGNiG 4830 – PGNiG Deepsea Yantai Marine
Own Experience
Operational 6608/1-1 S
Copernicus
Rig move 29/08/2022 All tubulars were backloaded from the rig and mud and bulk tanks emptied. The rig was deballasted to . . .
Phil Hardy / Morten Laget
PDF Edit