| Operator | Rig | Discipline / Origin | Project Phase | Well | Section | Date | What Happened | |
|---|---|---|---|---|---|---|---|---|
Wellesley
5937 – Wellesley
|
Deepsea Yantai | Drilling Own Experience INTERNAL |
Operational | 35/10-10S Carmen |
Other | 24/10/2023 |
During operation several MoC’s were made. A link to the risk register was enclosed in the MoC . . . Åse Kristin Pettersen |
PDF Edit |
Wellesley
5936 – Wellesley
|
Deepsea Yantai | Marine Own Experience |
Operational | 35/10-10S Carmen |
CAN-Ductor | 23/10/2023 |
Risk of WOW during Carmen CAN-Ductor installation and recovery leading to Wellesley being . . . Stian Engvik / Morten Laget |
PDF Edit |
DNO
5927 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
N/A | 19/09/2023 |
Mud cooler was used frequently throughout the wells. It was mobilized during Eirik and rigged up . . . John Langelandsvik / Morten Laget |
PDF Edit |
DNO
5912 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
N/A | 06/09/2023 |
Plugging of transfer lines when taking Microbar from vessels several times. John Langelandsvik / Morten Laget |
PDF Edit |
DNO
5870 – DNO
|
Deepsea Yantai | Drilling | Operational | 25/7-11 S Norma |
31/07/2023 |
Due to build up of cuttings around the wellhead after drilling pilot hole the marker buoys was . . . Drilling Engineer / Morten Laget |
PDF Edit | |
DNO
5862 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
When displacing the 26″ hole at TD a large volume of WBM was needed. And due to VDL the mud column . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5852 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
The pH meter showed indications of cement in return (pH value of 11.6-12.3). Due to poor visibility . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5853 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
After the cement of the 30″ conductor was set up the WHRT was released and POOH. Movement was seen . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5856 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
Used the ROV dredging around the conductor after drilling the 9 7/8″ Pilot hole. The cleaning with . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5857 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
Due to problems with cement around the conductor and movement in conductor a clamp-on inclinometer . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5858 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
Due to problems with cement around the conductor and movement in conductor a Bullseye bracket from . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5860 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Planning | 25/7-11 S Norma |
Top hole | 30/07/2023 |
One of the stop collars fell of when it was picked up from the boat. When laying down the . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5861 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
Difficult to see cement in return due to poor visibility at seabed. pH sniffer indicated cement in . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5869 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Surface section | 30/07/2023 |
From the start of the section after the FIT, delivery of cuttings to the ISO tanks using the CCBs . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5868 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Surface section | 30/07/2023 |
The drill commenced with the Driller pressuring up the well with 30 bar.
The classic method of . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5866 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Planning | 25/7-11 S Norma |
Surface section | 30/07/2023 |
Difficulties with logistics to separate the joints below 11.5 m and the joints longer due to limited . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5863 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Top hole | 30/07/2023 |
Everything went according to plan, no hole problems. Not much mud left. Drilling Engineer / Morten Laget |
PDF Edit |
DNO
5865 – DNO
|
Deepsea Yantai | Drilling Own Experience |
Operational | 25/7-11 S Norma |
Surface section | 30/07/2023 |
Problems in start of 17 1/2″ Section with plug in blower system to ISO tanks. Few skips in field. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5845 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
P&A | 12/07/2023 |
Pulled casing hanger with upper annular closed and C&K lines closed. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5844 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10 A Carmen |
Production section | 10/07/2023 |
Needed several trips with the tool up in the casing to cool it down. Drilling Engineer / Morten Laget |
PDF Edit |
NO LLs for INEOS