Lessons Learned749

Operator Rig Discipline / Origin Project Phase Well Section Date What Happened
DNO 5909 – DNO Deepsea Yantai Drilling Operational 25/7-11 S
Norma
P&A 05/09/2023 Due to high percentage of gas in the mud return the interface had to go over the shaker system and . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5839 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Intermediate section 20/06/2023 The cement didn’t set up as expected.
Drilling Engineer / Morten Laget
PDF Edit
PGNiG 4901 – PGNiG Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
P&A 14/09/2022 The heating cabinet in the logging unit does not work as required, not able to change the . . .
Drilling Engineer / Morten Laget
PDF Edit
INEOS 3405 – INEOS Borgland Dolphin Drilling
Own Experience
Operational PL937
Fat Canyon
Top hole 02/10/2021 A 30 m3 viscous freshwater spacer was pumped ahead of the cement to avoid contamination from sea . . .
/
PDF Edit
DNO 2108 – DNO Borgland Dolphin Drilling
Own Experience
Operational 2/5-15
Gomez
Intermediate section 05/09/2021 The PAB system failed before the cement job due to water ingress inside the unit which caused some . . .
Drilling Supervisor / Morten Laget
PDF Edit
DNO 2013 – DNO Borgland Dolphin Drilling
Experience Transfer Meeting
Operational 2/5-15
Gomez
Top hole 14/08/2021 From among cementers it was decided to disconnect the dust collector before this job. The surge . . .
What does ETM mean?
Drilling Supervisor / Morten Laget
PDF Edit
Wellesley 256 – Wellesley Transocean Arctic Drilling Operational 35/4-2
Songesand
Production section 16/06/2020 The cement slurry for the 9 5/8″ casing was thick/sticky and caused cement pump suction problems . . .
PDF Edit
PGNiG 379 – PGNiG Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Cut of 9-5/8” casing close to/above uncemented weak sand interval (w/ minor 5% gas). Resulted in . . .
PDF Edit
PGNiG 386 – PGNiG Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Excellent cement performances throughout operations (except the first KOP due to losses, weak . . .
PDF Edit
Faroe 287 – Faroe Transocean Arctic Drilling Operational 31/7-3 S
Brasse
Top hole 02/10/2019 Had to lay out one joint of fibreglass innerstring due to not able to M/U connection. No visible . . .
PDF Edit
DNO 305 – DNO Island Innovator Drilling Operational 6507/7-16 S
Canela
Top hole 07/01/2019 Conductor set up early. Had to order out more dispersant chemicals for the 20″ cement job due to . . .
PDF Edit
DNO 306 – DNO Island Innovator Drilling Operational 6507/7-16 S
Canela
Top hole 07/01/2019 The cement design was updated with reduced lead and increased tail slurry to provide better support . . .
PDF Edit
DNO 308 – DNO Island Innovator Drilling Planning 6507/7-16 S
Canela
Pilot hole section 07/01/2019 Pilot hole drilled to TD before identifying shallow gas. Resulted in having to order out more . . .
PDF Edit
DNO 310 – DNO Island Innovator Drilling Planning 6507/7-16 S
Canela
Surface section 07/01/2019 Not optimal cement recipe, needed 25 min to clean tanks between lead and tail slurry.
PDF Edit
DNO 311 – DNO Island Innovator Drilling Planning 6507/7-16 S
Canela
Surface section 07/01/2019 Cement slurry was changed to a gas-tigh slurry due to encountering shallow gas in pilot hole. Due to . . .
PDF Edit