| Operator | Rig | Discipline / Origin | Project Phase | Well | Section | Date | What Happened | |
|---|---|---|---|---|---|---|---|---|
DNO
5909 – DNO
|
Deepsea Yantai | Drilling | Operational | 25/7-11 S Norma |
P&A | 05/09/2023 |
Due to high percentage of gas in the mud return the interface had to go over the shaker system and . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5839 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Intermediate section | 20/06/2023 |
The cement didn’t set up as expected. Drilling Engineer / Morten Laget |
PDF Edit |
PGNiG
4901 – PGNiG
|
Deepsea Yantai | Drilling | Operational | 6608/1-1 S Copernicus |
P&A | 14/09/2022 |
The heating cabinet in the logging unit does not work as required, not able to change the . . . Drilling Engineer / Morten Laget |
PDF Edit |
INEOS
3405 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | PL937 Fat Canyon |
Top hole | 02/10/2021 |
A 30 m3 viscous freshwater spacer was pumped ahead of the cement to avoid contamination from sea . . . / |
PDF Edit |
DNO
2108 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Intermediate section | 05/09/2021 |
The PAB system failed before the cement job due to water ingress inside the unit which caused some . . . Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2013 – DNO
|
Borgland Dolphin | Drilling Experience Transfer Meeting |
Operational | 2/5-15 Gomez |
Top hole | 14/08/2021 |
From among cementers it was decided to disconnect the dust collector before this job. The surge . . . What does ETM mean? Drilling Supervisor / Morten Laget |
PDF Edit |
Wellesley
256 – Wellesley
|
Transocean Arctic | Drilling | Operational | 35/4-2 Songesand |
Production section | 16/06/2020 |
The cement slurry for the 9 5/8″ casing was thick/sticky and caused cement pump suction problems . . . |
PDF Edit |
PGNiG
379 – PGNiG
|
Deepsea Nordkapp | Drilling | Operational | 6507/5-9 S, 6507/5-9 A Shrek |
Production section | 22/10/2019 |
Cut of 9-5/8” casing close to/above uncemented weak sand interval (w/ minor 5% gas). Resulted in . . . |
PDF Edit |
PGNiG
386 – PGNiG
|
Deepsea Nordkapp | Drilling | Operational | 6507/5-9 S, 6507/5-9 A Shrek |
Production section | 22/10/2019 |
Excellent cement performances throughout operations (except the first KOP due to losses, weak . . . |
PDF Edit |
Faroe
287 – Faroe
|
Transocean Arctic | Drilling | Operational | 31/7-3 S Brasse |
Top hole | 02/10/2019 |
Had to lay out one joint of fibreglass innerstring due to not able to M/U connection. No visible . . . |
PDF Edit |
DNO
305 – DNO
|
Island Innovator | Drilling | Operational | 6507/7-16 S Canela |
Top hole | 07/01/2019 |
Conductor set up early. Had to order out more dispersant chemicals for the 20″ cement job due to . . . |
PDF Edit |
DNO
306 – DNO
|
Island Innovator | Drilling | Operational | 6507/7-16 S Canela |
Top hole | 07/01/2019 |
The cement design was updated with reduced lead and increased tail slurry to provide better support . . . |
PDF Edit |
DNO
308 – DNO
|
Island Innovator | Drilling | Planning | 6507/7-16 S Canela |
Pilot hole section | 07/01/2019 |
Pilot hole drilled to TD before identifying shallow gas. Resulted in having to order out more . . . |
PDF Edit |
DNO
310 – DNO
|
Island Innovator | Drilling | Planning | 6507/7-16 S Canela |
Surface section | 07/01/2019 |
Not optimal cement recipe, needed 25 min to clean tanks between lead and tail slurry. |
PDF Edit |
DNO
311 – DNO
|
Island Innovator | Drilling | Planning | 6507/7-16 S Canela |
Surface section | 07/01/2019 |
Cement slurry was changed to a gas-tigh slurry due to encountering shallow gas in pilot hole. Due to . . . |
PDF Edit |
NO LLs for INEOS