| Operator | Rig | Discipline / Origin | Project Phase | Well | Section | Date | What Happened | |
|---|---|---|---|---|---|---|---|---|
DNO
2209 – DNO
|
Borgland Dolphin | External Environment Own Experience |
Planning | 2/5-15 Gomez |
P&A | 06/10/2021 |
Due to potential WoW it was considered to leave the well and for DNO to join Oceaneering WH cutting . . . Christina Sæland Rødne / Christina Sæland Rødne |
PDF Edit |
DNO
2196 – DNO
|
Borgland Dolphin | Logistics | 2/5-15 Gomez |
04/10/2021 |
Backloaded with lack of information. Sent to wrong vendor/handled wrong. The casing was mistakenly . . . Martin Vikse / Morten Laget |
PDF Edit | ||
DNO
2130 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
P&A | 19/09/2021 |
1 hr extra rig time was unnecessarily spent to make up x-over to the RT before it could be made up . . . Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2305 – DNO
|
Borgland Dolphin | Logistics Own Experience |
Operational | 2/5-15 Gomez |
P&A | 15/09/2021 |
Missing Protectors for 13-3/8″ Casing Johan Kjos-Hanssen / Morten Laget |
PDF Edit |
DNO
2108 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Intermediate section | 05/09/2021 |
The PAB system failed before the cement job due to water ingress inside the unit which caused some . . . Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2107 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Top hole | 03/09/2021 |
Marker buoys too close to the hole, Fell inn and got drilled to bits. ROV use the marker buoys for . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
2106 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Surface section | 31/08/2021 |
Drilled 12 ¼” hole with Smith XZ616 AxeBlade PDC bit from 1613 m to 2895 m in a vertical hole. . . . Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2099 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Production section | 29/08/2021 |
The NORM instrument was found finally found on the drillfloor, however in an unmarked black . . . Drilling Engineer / Morten Laget |
PDF Edit |
DNO
2098 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Surface section | 27/08/2021 |
Unable to set seal assembly after 13 3/8″ hanger was landed. Attempted several times to pressure up . . . Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2094 – DNO
|
Borgland Dolphin | Logistics Own Experience |
Operational | 2/5-15 Gomez |
Reservoir section | 23/08/2021 |
Prior to mobilization of 8-1/2″ BHA, Coring and Wireline tools we held a aligmnement meeting to . . . Johan Kjos-Hanssen |
PDF Edit |
DNO
2096 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Surface section | 22/08/2021 |
DrilQuip MPT and BOP test tool was sent out without pup joints. Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2015 – DNO
|
Borgland Dolphin | Drilling Experience Transfer Meeting |
Operational | 2/5-15 Gomez |
Surface section | 14/08/2021 |
All handling subs had 5 1/2″ size. Had to spend rig time and expose rig crew in red zone changing . . . Contact all vendors that deliver tools with handling subs to Borgland Dolphin Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2014 – DNO
|
Borgland Dolphin | Drilling Experience Transfer Meeting |
Operational | 2/5-15 Gomez |
Surface section | 14/08/2021 |
The Franks split bushing spider (SBS) did not fit inside the EMSCO rotary table on Borgland Dolphin. Get in contact with Franks coordinator in town? Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2013 – DNO
|
Borgland Dolphin | Drilling Experience Transfer Meeting |
Operational | 2/5-15 Gomez |
Top hole | 14/08/2021 |
From among cementers it was decided to disconnect the dust collector before this job. The surge . . . What does ETM mean? Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2011 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Rig move | 12/08/2021 |
Scope of work was not sent to OIM or DSV before job. Two men from Schlumberger arrived at rig to . . . Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2012 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Top hole | 12/08/2021 |
ROV was only equipped with standard jetting tool with low flowrate, unable to remove larger amounts . . . Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2010 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Top hole | 12/08/2021 |
We could not store enough Tuned Light cement on two cmt silos on the rig to get the required volume . . . Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
1436 – DNO
|
Borgland Dolphin | External Environment NEA Q&A |
Planning | 2/5-15 Gomez |
23/04/2021 |
Hearing comment from Directorate of Fisheries: The ERACA/AfD lack information about sea mammals that . . . Christina Sæland Rødne / Christina Sæland Rødne |
PDF Edit | |
DNO
1435 – DNO
|
Borgland Dolphin | External Environment NEA Q&A |
Planning | 2/5-15 Gomez |
23/04/2021 |
Hearing comment from Directorate of Fishery: The ERACA lacks information about fishing/fishery . . . Christina Sæland Rødne / Christina Sæland Rødne |
PDF Edit | |
DNO
1434 – DNO
|
Borgland Dolphin | External Environment NEA Q&A |
Planning | 2/5-15 Gomez |
23/04/2021 |
Subunit C in PL006C not available in Brønnøysundregisteret. Christina Sæland Rødne / Christina Sæland Rødne |
PDF Edit |
NO LLs for INEOS