Report No. |
2209 |
Discipline/Origin |
External Environment |
Well |
Gomez |
Date created |
2021/10/06 |
Project Phase |
Planning |
LL Type/Classification |
Cut & pull |
Due to potential WoW it was considered to leave the well and for DNO to join Oceaneering WH cutting campaign later this year. Oceaneering are using cutting sand for their operations, and must be applied for to NEA. The cuttings sand is classified as yellow, and this is a focus area from NEA. Required Environmental coordinator to gather information and prepare last-minute application to NEA, with little time because of short determination time to move the rig or not.
Plan to cut well head from rig with knives.
Consider to apply for cuttings sand as a contingency option, especially for autumn and winter operations.
Risk and discuss it for every project.
Carried out according to initial plan
Plan to cut well head from rig with knives.
Consider to apply for cuttings sand as a contingency option, especially for autumn and winter operations.
Risk and discuss it for every project.
Carried out according to initial plan
NO LLs for INEOS