Lesson Learned


No user selected
Report No.

294

Discipline/Origin

Drilling
No origin

Well

Brasse
31/7-3 A

Date created

2019/10/03
2556 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Transocean Arctic

What happened in Reservoir section:
After engaging fish in overshot an electrical release of cable head (ECRD) was planned. Due to shorting in cable unable to release ECRD. Unable to determine where shorting was along the cable (kortslutning). Discussed plan forward and decided to perform a reverse cut and thread operation.

What Was Planned

Wireline cut and thread

What Was Learned

NA

What Actions Are Required

NA

EDITOR

CLOSE LL (testing)