Lesson Learned


By: Drilling Engineer
Report No.

5142

Discipline/Origin

Drilling
No origin

Well

Carmen
35/10-10S

Date created

2023/04/14
1266 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
No classification

Deepsea Yantai

What happened in Surface section:
NPT: 0.75 hrs Cost: 156 250 NOK Downtime due to Work String/Jar/Stuck Equipment. Freed stuck BHA with bit at 1129 m: – Observed string stall out immediately after bit drilled through shoe at 1128 m. – Attempted to free string with 12-15 t OP, no-go. – Set down 10 t weight, bit would not move down. – Unable to re-initiate rotation with 30 kNm max torque setting on TDS, string stalled out. Increased maximum to 50 kNm, string stalled out. – Continued to work string with higher OP. BHA came free with 45 t OP. Pulled bit up to 1125 m. – Re-initiated rotation and staged up to 90 RPM / 1-2 kNm. – Slowly worked bit down to 1129 m. Torque increased to 3-4 kNm.

What Was Planned

Drill/Mill shoetrack & Cement

EDITOR

CLOSE LL (testing)

New Lesson Learned

You do not have permission to view this form.