Report No. |
5833 |
Discipline/Origin |
Other |
Well |
Carmen |
Date created |
2023/06/13 |
Project Phase |
Operational |
LL Type/Classification |
BOP |
Unable to lift the BOP elevator with LMRP past fixed guide/bumper beams in moonpool. LMRP diameter to large. Had to work over side in basket.
To pull the LMRP to change out the annular. The plan was to skid the LMRP to fixed guide, floor to work on changing out the UAP.
To pull the LMRP to change out the annular. The plan was to skid the LMRP to fixed guide, floor to work on changing out the UAP.
NO LLs for INEOS