Report No. |
2319 |
Discipline/Origin |
Drilling |
Well |
Fat Canyon |
Date created |
2021/12/09 |
Project Phase |
Planning |
LL Type/Classification |
Planning |
Encountered several shallow gas zones. The decision to use and mobilize foam cement took some time. This forced the client to take on extremely expensive spot-market vessels to deliver equipment and rig up.
Drill top hole section without encountering shallow gas
In places where shallow gas is somewhat expected, foam cement equipment should be mobilized and kept ready incase its needed. It is cheaper to start mobilizing equipment and demobilizing it, rather then having operational downtime and also taking on spot-market vessels.
No actions required as this is usally up to the clients. However, it can be recommended to different clients based on this experience.
Drill top hole section without encountering shallow gas
In places where shallow gas is somewhat expected, foam cement equipment should be mobilized and kept ready incase its needed. It is cheaper to start mobilizing equipment and demobilizing it, rather then having operational downtime and also taking on spot-market vessels.
No actions required as this is usally up to the clients. However, it can be recommended to different clients based on this experience.