Report No. |
2316 |
Discipline/Origin |
Drilling |
Well |
Fat Canyon |
Date created |
2021/12/09 |
Project Phase |
Operational |
LL Type/Classification |
Planning |
Extremeley slow drilling. At worst it was down to 1-2m/hr. At best it was 9-12m/hr.
Drill 12 1/4″ hole and set 9 5/8″ casing effortlessly in mainbore (and the subsequent sidetrack).
WBM mud in the clays in Haltenbanken (well known area where all operators try to avoid the use of WBM). Sticky clay, balled up bits/stabs, swelling clays, tight hole, slow progress and finally; stuck casing as a result. This added weeks of operational “downtime” due to being forced to cut casing casing and perform sidetrack drilling. Which also saw extremely slow progress, tight spots, balled up bits and almost a stuck sidetrack casing as well.
In these areas OBM should always be used. Always.
Drill 12 1/4″ hole and set 9 5/8″ casing effortlessly in mainbore (and the subsequent sidetrack).
WBM mud in the clays in Haltenbanken (well known area where all operators try to avoid the use of WBM). Sticky clay, balled up bits/stabs, swelling clays, tight hole, slow progress and finally; stuck casing as a result. This added weeks of operational “downtime” due to being forced to cut casing casing and perform sidetrack drilling. Which also saw extremely slow progress, tight spots, balled up bits and almost a stuck sidetrack casing as well.
In these areas OBM should always be used. Always.
NO LLs for INEOS