| Operator | Rig | Discipline / Origin | Project Phase | Well | Section | Date | What Happened | |
|---|---|---|---|---|---|---|---|---|
Wellesley
5937 – Wellesley
|
Deepsea Yantai | Drilling Own Experience INTERNAL |
Operational | 35/10-10S Carmen |
Other | 24/10/2023 |
During operation several MoC’s were made. A link to the risk register was enclosed in the MoC . . . Åse Kristin Pettersen |
PDF Edit |
Wellesley
5936 – Wellesley
|
Deepsea Yantai | Marine Own Experience |
Operational | 35/10-10S Carmen |
CAN-Ductor | 23/10/2023 |
Risk of WOW during Carmen CAN-Ductor installation and recovery leading to Wellesley being . . . Stian Engvik / Morten Laget |
PDF Edit |
Wellesley
5845 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
P&A | 12/07/2023 |
Pulled casing hanger with upper annular closed and C&K lines closed. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5844 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10 A Carmen |
Production section | 10/07/2023 |
Needed several trips with the tool up in the casing to cool it down. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5839 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Intermediate section | 20/06/2023 |
The cement didn’t set up as expected. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5837 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
Surface section | 16/06/2023 |
Pups could not be run from aux using the “handshake” technique (too short for the Hydraracker) and . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5833 – Wellesley
|
Deepsea Yantai | Other | Operational | 35/10-10S Carmen |
N/A | 13/06/2023 |
Unable to lift the BOP elevator with LMRP past fixed guide/bumper beams in moonpool. LMRP diameter . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5186 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
Reservoir section | 20/05/2023 |
Drilled 8 1/2″ section with 5 7/8″ DP with 1400-1500 lpm and low ROP, saw ECD up to 18 points.
MW . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5185 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
Reservoir section | 18/05/2023 |
On second MDT got stuck with Saturn packer and had to release electrical cable head and fish . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5184 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
Reservoir section | 18/05/2023 |
Managed to fish roughly 1/2 of junk in hole that accumulated in junk basket (some was seen over . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5176 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Reservoir section | 08/05/2023 |
When coring 54 m cores, during connection the kick stand was removed a single joint was connected . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5175 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Reservoir section | 08/05/2023 |
Followed the HPHT manual for fingerprinting. Fingerprinter found some improvement point to the . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5174 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Reservoir section | 08/05/2023 |
Treated the mud for the second and subsequent runs circulating BU after cutting cores. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5173 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Reservoir section | 08/05/2023 |
Crew not participating in the pre-job meeting but involved in L/D core. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5171 – Wellesley
|
Deepsea Yantai | Operational | 35/10-10S Carmen |
N/A | 06/05/2023 |
The BOP test tool was not ready to run. No DQ onboard and no status on the tool before they left the . . . Drilling Engineer / Morten Laget |
PDF Edit | |
Wellesley
5161 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Reservoir section | 26/04/2023 |
Weighted up the mud by mixing in a heavier mud. The volume of heavier mud can partially compensate . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5157 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
Production section | 24/04/2023 |
It was done before the cementer got the change to da a pre-job check / install bypass baffle etc. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5158 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Reservoir section | 24/04/2023 |
NPT: 7.75 hrs
Cost: 1 614 000 NOK
Cyber chair stopped functioning.
On Odfjell. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5160 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Production section | 24/04/2023 |
Lube mud had 1.34 sg when taken up.
Needed to weight it down to ± 1.25 sg.
New lube mud for 12 . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5159 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Production section | 24/04/2023 |
Downtime due to reduced ROP after going to max ROP of 75 m/hr:
– Started with 30 m/hr
– Jumped up . . . Drilling Engineer / Morten Laget |
PDF Edit |