Lessons Learned749

Operator Rig Discipline / Origin Project Phase Well Section Date What Happened
Wellesley 5937 – Wellesley Deepsea Yantai Drilling
Own Experience
INTERNAL
Operational 35/10-10S
Carmen
Other 24/10/2023 During operation several MoC’s were made. A link to the risk register was enclosed in the MoC . . .
Åse Kristin Pettersen
PDF Edit
Wellesley 5936 – Wellesley Deepsea Yantai Marine
Own Experience
Operational 35/10-10S
Carmen
CAN-Ductor 23/10/2023 Risk of WOW during Carmen CAN-Ductor installation and recovery leading to Wellesley being . . .
Stian Engvik / Morten Laget
PDF Edit
Wellesley 5845 – Wellesley Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
P&A 12/07/2023 Pulled casing hanger with upper annular closed and C&K lines closed.
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5844 – Wellesley Deepsea Yantai Drilling Operational 35/10-10 A
Carmen
Production section 10/07/2023 Needed several trips with the tool up in the casing to cool it down.
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5839 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Intermediate section 20/06/2023 The cement didn’t set up as expected.
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5837 – Wellesley Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
Surface section 16/06/2023 Pups could not be run from aux using the “handshake” technique (too short for the Hydraracker) and . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5833 – Wellesley Deepsea Yantai Other Operational 35/10-10S
Carmen
N/A 13/06/2023 Unable to lift the BOP elevator with LMRP past fixed guide/bumper beams in moonpool. LMRP diameter . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5186 – Wellesley Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
Reservoir section 20/05/2023 Drilled 8 1/2″ section with 5 7/8″ DP with 1400-1500 lpm and low ROP, saw ECD up to 18 points. MW . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5185 – Wellesley Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
Reservoir section 18/05/2023 On second MDT got stuck with Saturn packer and had to release electrical cable head and fish . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5184 – Wellesley Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
Reservoir section 18/05/2023 Managed to fish roughly 1/2 of junk in hole that accumulated in junk basket (some was seen over . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5176 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 When coring 54 m cores, during connection the kick stand was removed a single joint was connected . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5175 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 Followed the HPHT manual for fingerprinting. Fingerprinter found some improvement point to the . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5174 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 Treated the mud for the second and subsequent runs circulating BU after cutting cores.
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5173 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 Crew not participating in the pre-job meeting but involved in L/D core.
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5171 – Wellesley Deepsea Yantai Operational 35/10-10S
Carmen
N/A 06/05/2023 The BOP test tool was not ready to run. No DQ onboard and no status on the tool before they left the . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5161 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 26/04/2023 Weighted up the mud by mixing in a heavier mud. The volume of heavier mud can partially compensate . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5157 – Wellesley Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
Production section 24/04/2023 It was done before the cementer got the change to da a pre-job check / install bypass baffle etc.
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5158 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 24/04/2023 NPT: 7.75 hrs Cost: 1 614 000 NOK Cyber chair stopped functioning. On Odfjell.
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5160 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Production section 24/04/2023 Lube mud had 1.34 sg when taken up. Needed to weight it down to ± 1.25 sg. New lube mud for 12 . . .
Drilling Engineer / Morten Laget
PDF Edit
Wellesley 5159 – Wellesley Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Production section 24/04/2023 Downtime due to reduced ROP after going to max ROP of 75 m/hr: – Started with 30 m/hr – Jumped up . . .
Drilling Engineer / Morten Laget
PDF Edit