| Operator | Rig | Discipline / Origin | Project Phase | Well | Section | Date | What Happened | |
|---|---|---|---|---|---|---|---|---|
Wellesley
5843 – Wellesley
|
Deepsea Yantai | Drilling | Planning | 35/10-10S Carmen |
Intermediate section | 20/06/2023 |
It was separated into two runs. The cup tester did not fit in the 9 7/8″ wearbushing installed in . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5842 – Wellesley
|
Deepsea Yantai | Drilling | Planning | 35/10-10S Carmen |
Intermediate section | 20/06/2023 |
Had some stringer in the bottom of the 12 1/4″ Section and had to work the csg hgr w/seal assy up . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5841 – Wellesley
|
Deepsea Yantai | Drilling | Planning | 35/10-10S Carmen |
Intermediate section | 20/06/2023 |
The CHSART was run with the pup sent out with the tool. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5840 – Wellesley
|
Deepsea Yantai | Drilling | Planning | 35/10-10S Carmen |
Intermediate section | 20/06/2023 |
It was run according to tally. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5839 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Intermediate section | 20/06/2023 |
The cement didn’t set up as expected. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5145 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Intermediate section | 16/04/2023 |
FIT was a success. Shaved off 1.75 hrs compared to the test at 20″ shoe. 2.5 hrs vs 0.75 hrs. . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5141 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
Intermediate section | 13/04/2023 |
Not approved pressure test. Downtime to drilling contractor. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5114 – Wellesley
|
Deepsea Yantai | Drilling | Operational | Eirik (OMV) | Intermediate section | 30/03/2023 |
Experienced higher pore pressure earlier than expected. Had enough to weight up active from 1,44 to . . . Sander Schaathun / Morten Laget |
PDF Edit |
PGNiG
4841 – PGNiG
|
Deepsea Yantai | Drilling Own Experience |
Operational | 6608/1-1 S | Intermediate section | 04/09/2022 |
Had to switch to a BX elevator Drilling Engineer / Morten Laget |
PDF Edit |
PGNiG
4762 – PGNiG
|
Deepsea Yantai | Drilling Own Experience |
Planning | Copernicus | Intermediate section | 22/08/2022 |
4-string contingency scenario was miscommunicated and we did not have the 13 3/8″ SSRII landing . . . Richard Mollison / Morten Laget |
PDF Edit |
INEOS
2300 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Planning | 6306/3-1 S Fat Canyon |
Intermediate section | 09/11/2021 |
Initial planned centralizer program of using 1 centralizer every other joint above shoetrack to top . . . Drilling Supervisor / Morten Laget |
PDF Edit |
INEOS
2280 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | 6306/3-1 S Fat Canyon |
Intermediate section | 07/11/2021 |
Had initially many problems with Franks equipment that did not work, and cold windy weather outside . . . Drilling Supervisor / Morten Laget |
PDF Edit |
INEOS
2279 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Planning | 6306/3-1 S Fat Canyon |
Intermediate section | 07/11/2021 |
9 5/8″ float shoe filled up with mud. Drilling Supervisor / Morten Laget |
PDF Edit |
INEOS
2278 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | 6306/3-1 S Fat Canyon |
Intermediate section | 07/11/2021 |
We had several faults on the Franks equipment. This led to troubleshooting, phone calls to town, . . . Drilling Supervisor / Morten Laget |
PDF Edit |
INEOS
2277 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | 6306/3-1 S Fat Canyon |
Intermediate section | 07/11/2021 |
It took 4,25 hrs to rig it up on Borgland Dolphin. The rigging up of casing tong and FMS slips . . . Drilling Supervisor / Morten Laget |
PDF Edit |
INEOS
2276 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | 6306/3-1 S Fat Canyon |
Intermediate section | 07/11/2021 |
Decided to use the Franks casing circulating tool FA-1 Drilling Supervisor / Morten Laget |
PDF Edit |
INEOS
2275 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | 6306/3-1 S Fat Canyon |
Intermediate section | 06/11/2021 |
Had two bit trips with very low, down to 1 m/hr ROP Drilling Supervisor / Morten Laget |
PDF Edit |
INEOS
3407 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | PL937 Fat Canyon |
Intermediate section | 04/11/2021 |
ROP in 12 1/4″ section dropped to almost nothing at +/- 1900 m. Drilling parameters were varied, and . . . / |
PDF Edit |
INEOS
2269 – INEOS
|
Borgland Dolphin | Drilling Own Experience |
Operational | 6306/3-1 S Fat Canyon |
Intermediate section | 31/10/2021 |
ROP dropped from 50 m/hr to 1 m/hr Drilling Supervisor / Morten Laget |
PDF Edit |
DNO
2108 – DNO
|
Borgland Dolphin | Drilling Own Experience |
Operational | 2/5-15 Gomez |
Intermediate section | 05/09/2021 |
The PAB system failed before the cement job due to water ingress inside the unit which caused some . . . Drilling Supervisor / Morten Laget |
PDF Edit |
NO LLs for INEOS