| Operator | Rig | Discipline / Origin | Project Phase | Well | Section | Date | What Happened | |
|---|---|---|---|---|---|---|---|---|
Wellesley
5145 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Intermediate section | 16/04/2023 |
FIT was a success. Shaved off 1.75 hrs compared to the test at 20″ shoe. 2.5 hrs vs 0.75 hrs. . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5144 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 16/04/2023 |
NPT: 1.25 hrs
Cost: 260 417 NOK
Repaired hydraulic leak on PS-30 slips. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5143 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 16/04/2023 |
NPT: 1.25 hrs
Cost: 260 417 NOK
Downtime due to reaming and reduced ROP.
Drilled stand from . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5142 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 14/04/2023 |
NPT: 0.75 hrs
Cost: 156 250 NOK
Downtime due to Work String/Jar/Stuck Equipment.
Freed stuck . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5141 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
Intermediate section | 13/04/2023 |
Not approved pressure test. Downtime to drilling contractor. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5140 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 13/04/2023 |
NPT: 0.75 hrs
Cost: 156 250 NOK
Observed poor make-up of jt #204 into jt #111:
– No shoulder . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5139 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 13/04/2023 |
NPT: 1.25 hrs
Cost: 260 417 NOK
Performed mechanical repair on make/break cylinder on casing . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5138 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 13/04/2023 |
Total NPT: 11.25 hrs
Cost: 2 343 750 NOK
LARS lost communication with SubSea pump. Troubleshot . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5134 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 |
It was difficult to stab in the 20″ casing joints with 15 ft bails and rig movement Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5124 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 |
Run mud mat with buoyancy marker. Mud mat covered in soil after completing RMR operation Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5125 – Wellesley
|
Deepsea Yantai | Subsea | Operational | 35/10-10S Carmen |
Top hole | 10/04/2023 |
When opening the trawl protector with the ROV, one of the locking pins fell off. It was recovered to . . . Lene Lomeland / Morten Laget |
PDF Edit |
Wellesley
5126 – Wellesley
|
Deepsea Yantai | Operational | 35/10-10S Carmen |
Top hole | 10/04/2023 |
Ran mud mat from rig Drilling Engineer / Morten Laget |
PDF Edit | |
Wellesley
5127 – Wellesley
|
Deepsea Yantai | Drilling Own Experience |
Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 |
Not enough deckspace to place shoe and sting-in float. Had to be laid in riser bay. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5128 – Wellesley
|
Deepsea Yantai | Logistics | Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 |
Logistical problems when Shoe track joints are placed on top of all other CSG on the boat. Shoetrack . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5130 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 | Drilling Engineer / Morten Laget | PDF Edit |
Wellesley
5133 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 |
MWD/DD instructed drilling crew to break wrong connection when L/D 26″ BHA. As top part of assy was . . . Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5132 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 |
Lubricated OOH with 26″ BHA with 2000 lpm Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5129 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 10/04/2023 |
The 26″ section was drilled with 4×20/32 nozzles. Bit some balled up. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5131 – Wellesley
|
No Rig | Drilling | Operational | No well | Surface section | 10/04/2023 |
Difficulties passing 20″ CSG shoe through FMS. Engaged CRTi and pushed through. Drilling Engineer / Morten Laget |
PDF Edit |
Wellesley
5122 – Wellesley
|
Deepsea Yantai | Drilling | Operational | 35/10-10S Carmen |
Surface section | 09/04/2023 |
The shoetrack was made up to 27,500 ft.lbs. Drilling Engineer / Morten Laget |
PDF Edit |
NO LLs for INEOS